    Project 2007 Resource Pool (2007 XP)

    I am assigning a resource pool to a project. There are no resources in that project. The end date changes from Aug 4 to Aug 1.
    Can anyone give me a hint as to what might be wrong?

    - Kirsten

  2. #2
    4 Star Lounger
    Join Date
    Sep 2004
    Location
    Sacramento, California, USA
    Posts
    432
    Thanks
    0
    Thanked 0 Times in 0 Posts

    Re: Project 2007 Resource Pool (2007 XP)

    Have you made any base calendar changes in the resource pool file? When you assign a resource pool you have a choice on conflict for the pool to take precedence. If you selected for the pool file to take precedence and the base calendar for the pool file is different than the project base calendar it might effect the project file.

    Carla