    Hi,
    I want a field to show planned hours per task as of Status Date. I can use the Work field but that gives me the total hours per task. I want to see how many hours I planned as of the current date. Meaning, if I have a 4 days task, my work field will show 32 hours (8 hours/day x 4 days). I'm on day 2, I want a field to show me that I should have 16 hours of planned work. Then I can compare what my actual work is per day.

    Thanks,
    Deb

  2. #2
    4 Star Lounger
    Join Date
    Sep 2004
    Location
    Sacramento, California, USA
    Posts
    432
    Thanks
    0
    Thanked 0 Times in 0 Posts
    I used the Task Usage View to look at what you are wanting to display. I added the field called Remaining Work to the Task Usage Table. If your plan is updated as to what is complete it should show what you are looking for.

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •