    I have a simple task list with a set of deliverables at the bottom. Each deliverable is due right one of the above sections. I'd like to NOT set them to be due on a date so if the tasks change, it changes, without being wrong. All tasks are ASAP and few constraints.

    Tasks
    Task 1 Set
    Task 2 Set
    Task 3 Set
    Deliverables
    Deliverable 1 should level to be done right when Task 1 Set is complete. It has Task 1 set as a Predecessor.
    Deliverable 2 etc.

    Right now they level to show up starting after Task 3 Set.

    Help!

  2. #2
    Star Lounger
    Join Date
    Nov 2004
    Location
    San Diego, California, USA
    Posts
    95
    Thanks
    0
    Thanked 0 Times in 0 Posts
    What other Predecessors have you set? Are there any Summary-level tasks (e.g., Tasks, Deliverables, etc...)? Is there a Predecessor for the summary-level task? Other than the Predecessor for Deliverable 1, what Predecessors have you set?
    Don Liebman
    San Diego, CA 92115

  3. #3
    2 Star Lounger
    Join Date
    Jan 2003
    Location
    Greeley, Colorado
    Posts
    188
    Thanks
    8
    Thanked 1 Time in 1 Post
    Sorry to say that project is long gone and I don't exactly remember the details. Thanks for the reply.

    Quote Originally Posted by DonL View Post
    What other Predecessors have you set? Are there any Summary-level tasks (e.g., Tasks, Deliverables, etc...)? Is there a Predecessor for the summary-level task? Other than the Predecessor for Deliverable 1, what Predecessors have you set?