    With MSProj2k, I am designing a GANNT chart for a project to be implemented in a country where the weekends are Thursday & Friday.

    How can I configure this withing Project?

    Thanks,

    m.q.

  2. #2
    Super Moderator WebGenii's Avatar
    Join Date
    Jan 2001
    Location
    Redcliff, Alberta, Canada
    Posts
    4,066
    Thanks
    2
    Thanked 5 Times in 5 Posts

    Re: Change Weekend Days... (2000)

    Try going to the Tools, Change Working Time and change the working days on the Standard Project Calendar. You can select all Thursdays & Fridays by clicking on the top of the weekly calendar. Then make them non-working time. Change Sat/Sun to working time.
    Hope this helps.
    Attached Images Attached Images
    [b]Catharine Richardson (WebGenii)
    WebGenii Home Page
    Moderator: Spreadsheets, Other MS Apps, Presentation Apps, Visual Basic for Apps, Windows Mobile

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •