    Baseline Rollup error

    Hi,

    I am facing this weird issue. In the attached MPP file that is baselined and currently under production (with actual time logged in it), I tried adding a new task and baselined it following the process of Tools-->Tracking--Set Baseline -->Baseline Selected tasks and checked both the checkboxes below it. I also selected the task and the summary tasks to baseline it. The problem I am facing is that instead of increasing the overall summary baseline by 65 hours (the added task is # 189, called "XYZ", with work = 65 hrs that needs to reflect in the baseline), it is reducing the overall baseline information.
    I checked the net and found that it is an issue. Just wanted to know what is the resolution? It would be impossible to start afresh - the plan is fairly large. We need to process this change request soon and get the plan maintained for reporting. Please help.

    Oh, and I am using MS Project Professional 2007 SP 2 MSO (not Server but the standalone client version).
    Attached Files Attached Files

Tags for this Thread

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •