    report project data for each resource

    I want to create a report for each resource on my project showing all the tasks they should be working on with dates. How do I do this?

  2. #2
    5 Star Lounger
    Join Date
    Dec 2009
    Location
    East Coast, USA
    Posts
    993
    Thanks
    8
    Thanked 43 Times in 43 Posts
    Some thoughts.....

    How many and kind of projects? How many tasks? Date ranges?

    What software is available ie. MS Excel, MS Project, QuickBase?

  3. #3
    2 Star Lounger
    Join Date
    Jan 2003
    Location
    Greeley, Colorado
    Posts
    188
    Thanks
    8
    Thanked 1 Time in 1 Post
    one project, 400 tasks with 15 resources, 6 months. excel, project, access, no QB

  4. #4
    New Lounger
    Join Date
    Feb 2010
    Location
    East Brunswick, NJ
    Posts
    15
    Thanks
    1
    Thanked 3 Times in 2 Posts

    Extract project data for resources

    Rob Gill's book "VBA Programming for Microsoft Office Project" has the answer on page 281. The book is worth the price and you get to download all of the code as a bonus.

    Norm