    Printing Gantt Chart from Filtered Date (Project 2000)

    Anyone know if there is a way to control how much of the Gantt Chart displays when I'm printing a filtered Table? I have only my completed tasks displayed but the Gantt Chart always displays from the Project Start Date. I want the first task on the table to be the top of the Gantt Chart in the Print window.

  2. #2
    Silver Lounger GARYPSWANSON's Avatar
    Join Date
    Aug 2001
    Location
    Frederick, Maryland, USA
    Posts
    1,788
    Thanks
    0
    Thanked 2 Times in 2 Posts

    Re: Printing Gantt Chart from Filtered Date (Project 2000)

    One option to start the printing at a time other then the start date is to select Print from the Main Menu and set the starting time to print in the Dates, From and Too in the Timescale.

    To limit the number of columns of data that are printed, go to File Page Setup View and indicate the number of rows to print.

    Hope this helps.
    Regards,

    Gary
    (It's been a while!)