    Rotating shifts (Project 2000)

    Calendar wise how do you normally handle people that rotate shifts and/or work
    weekends? Do you normally start with a 24-hr calendar and just plug in their
    schedule? What problems have you run into? Thank you for your help and
    opinions. Fay

  2. #2
    Star Lounger
    Join Date
    Oct 2001
    Location
    Ellettsville, Indiana, USA
    Posts
    76
    Thanks
    0
    Thanked 0 Times in 0 Posts

    Re: Rotating shifts (Project 2000)

    You can create "Base" calendars that include the hours that multiple resources will work and them assign them in the resource sheet to that "Base" calendar. For exemple, your technical team works weekends, so create a "Technical" calendar (tools, change working time, click new). Then, if one or two of those resources have special circumstances you can double click on the resource (in the resource shee) and select working times and input those special days off or hours.
    Hope it helps