    When entering resources names, MS Project seems to save the names in the order you enter them. This is Ok if you have a relatively small project, however, it is a bit a pain with large lists of resources.

    Is there anyway of (automatically?) organising the resource names in alphabetical order?

    PS: We have sorted the resource names in the resource sheet but this does not have any impact on the drop down list of resources.

  2. #2
    New Lounger
    Join Date
    Sep 2004
    Location
    Stockholm, Sweden
    Posts
    1
    Thanks
    0
    Thanked 0 Times in 0 Posts

    Re: Resource Ordering

    Sort the Resources by selecting "Sort/Sort by..." from the Project menu. There you'll find a checkbox for permanently re-ordering your resources - the drop-down listbox will use the ID ordering.

    /Lars H

  3. #3
    claudedaniel
    Guest

    Re: Resource Ordering

    Lars,

    Problem fixed. Thanks heaps - it has been bugging me [img]/w3timages/icons/yikes.gif[/img] for a while!

    Cheers,

    Claude [img]/w3timages/icons/smile.gif[/img]

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •