    rollup resource assignment data (Project 2000)

    Does anyone know how to roll up resource assignment data to the summary task? I have a project file that is really many tasks with the same underlying structure:

    sumtask1
    -plan
    -do
    -check

    sumtask2
    -plan
    -do
    -check


    Resources are assigned to the 'plan - do - check' tasks, and what I'd like to see is for the summary tasks, what the total work assigned to the resource for that summary task.

    -Joe

  2. #2
    Silver Lounger GARYPSWANSON's Avatar
    Join Date
    Aug 2001
    Location
    Frederick, Maryland, USA
    Posts
    1,788
    Thanks
    0
    Thanked 2 Times in 2 Posts

    Re: rollup resource assignment data (Project 2000)

    Try the View / Task Usage view. You could add the columns for resources if needed. You could also run a report.
    Regards,

    Gary
    (It's been a while!)

  3. #3
    New Lounger
    Join Date
    Apr 2002
    Posts
    4
    Thanks
    0
    Thanked 0 Times in 0 Posts

    Re: rollup resource assignment data (Project 2000)

    thanks, but that's not it - I want to see, for a summary task, one row for each resource that sums up its assignment information for all the subtasks.

    in my example, if I have a resource assigned to 'plan' for 10 hours, 'check' for 10 hours, then the assignment data for sumtask1 would be 20 hours for that resource.

    -Joe

  4. #4
    Silver Lounger GARYPSWANSON's Avatar
    Join Date
    Aug 2001
    Location
    Frederick, Maryland, USA
    Posts
    1,788
    Thanks
    0
    Thanked 2 Times in 2 Posts

    Re: rollup resource assignment data (Project 2000)

    The only other way I know that may work to do this is to export the MS Project Data to a database (Access works nicely) and relink the data between the MSP_Tasks and MSP_Assignments tables to get the results you want. You would also have to convert the work to hours.

    I will watch this string to see if anyone has an easier solution.
    Regards,

    Gary
    (It's been a while!)