I had a task scheduled to start on 2/5/01. It was to take 2 hrs (work) / .25 days(dur). The task was not started (and completed) until 2/9/01. I track time using the Resource Usage view by entering it the Timesheet. When I did this, it moved the task's Start Date to 2/9 and its duration to 1 day. Why? Also, if the time is coming from a Project Central Update, duration still increases to 1 day but resource units stay at 100%. Why the difference? Is this a bug?