Results 1 to 3 of 3
  1. #1
    New Lounger
    Join Date
    Jun 2002
    Posts
    3
    Thanks
    0
    Thanked 0 Times in 0 Posts

    Modifying MPD (2000/SR1)

    I have a program which goes into our time tracking system and modifies the Actual Work field in the assignments table.
    When i load project, I see the actual work in the assignment but it is not rolled up to the task or resource. Hitting F9 does not do this.
    I suspect I need a macro to go thru and force the calculations.
    HELP???

  2. #2
    Silver Lounger GARYPSWANSON's Avatar
    Join Date
    Aug 2001
    Location
    Frederick, Maryland, USA
    Posts
    1,788
    Thanks
    0
    Thanked 2 Times in 2 Posts

    Re: Modifying MPD (2000/SR1)

    You said <When i load project, I see the actual work in the assignment but it is not rolled up to the task or resource. Hitting F9 does not do this.>

    - Which screen are you using to review the data in MS Project when you indicate it is not rolling up?
    - I assume that you are importing the actual hours worked by resource into MS Project, is this correct?

    - Have you been able to get this to work?
    Regards,

    Gary
    (It's been a while!)

  3. #3
    New Lounger
    Join Date
    Jun 2002
    Posts
    3
    Thanks
    0
    Thanked 0 Times in 0 Posts

    Re: Modifying MPD (2000/SR1)

    I am entering the actual work into the assignment table.
    I view it looking at Resources Usage view with the column actual work added
    I got it to work by adding a macro:
    Sub CalcAllWork()
    Dim A As Assignment
    Dim Temp As Long
    For Temp = 1 To ActiveProject.Tasks.Count
    For Each A In ActiveProject.Tasks(Temp).Assignments
    A.ActualWork = A.ActualWork
    Next A
    Next Temp
    End Sub

Posting Permissions