    This is one of those questions that I thought was easy, until I tried to do it...

    I need to assign a resource to the whole project (using Project 2000). Unfortunately, you can't assign resources to the project summary task. Does anyone know of a neat way of doing this, apart from creating a summary task which encompasses the whole project?

    Paul Seaman
    IT Trainer (UK)

  2. #2

    Re: Assign Resource to a Project

    create a filter that says 'summary' 'does not equal' 'yes'
    select all desired rows
    open the task information dialog, select the resources tab, and make assignments for all selected rows.

    hope this helps.