    Does anyone have any experience using the calendar view with multiple projects? I would like to display the project name and the milestone as text in the bar. However, there does not seem to be a field for the name of the project. Also, is there a best way to show the bars when you have 4 multiple projects on one calendar view?

    Thank you,
    Kim

  2. #2
    Super Moderator WebGenii's Avatar
    Join Date
    Jan 2001
    Location
    Redcliff, Alberta, Canada
    Posts
    4,066
    Thanks
    2
    Thanked 5 Times in 5 Posts

    Re: Calendar View with Multiple Projects (MSP - 2000)

    I'd probably create a filter.

    Cheers
    [b]Catharine Richardson (WebGenii)
    WebGenii Home Page
    Moderator: Spreadsheets, Other MS Apps, Presentation Apps, Visual Basic for Apps, Windows Mobile

  3. #3
    3 Star Lounger
    Join Date
    Mar 2003
    Location
    Beddau, Mid Glamorgan, Wales
    Posts
    289
    Thanks
    0
    Thanked 0 Times in 0 Posts

    Re: Calendar View with Multiple Projects (MSP - 2000)

    The Project Summary Task will show the name(s) of the project(s) in Calendar view. (Tools/Options/View/ProjectSummaryTask).

    Tony.
    Regards,

    Tony
    [s] [/s]
    www.SylviArtist.com

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •