    Is there a way to get Summary Tasks to total custom number or cost fields, just like it does for the duration field?????

    Thanks in advance <img src=/S/crossfingers.gif border=0 alt=crossfingers width=17 height=16>

  2. #2
    3 Star Lounger
    Join Date
    Mar 2003
    Location
    Beddau, Mid Glamorgan, Wales
    Posts
    289
    Thanks
    0
    Thanked 0 Times in 0 Posts

    Re: Custom Fields (2002)

    I have Project 2000 - hope the solution is the same for XP.

    Go to Tools/Customise/Fields, select the type of field (Number, Costs etc), select your chosen field (eg Number1), then choose Sum from the Rollup combo.

    Tony.
    Regards,

    Tony
    [s] [/s]
    www.SylviArtist.com

  3. #3
    New Lounger
    Join Date
    Apr 2003
    Location
    Wellington, North Island, New Zealand
    Posts
    4
    Thanks
    0
    Thanked 0 Times in 0 Posts

    Re: Custom Fields (2002)

    Excellent - slight difference in 2002 in that there is a drop down list to choose the function from, and it is under the heading "Calculation for task and group summary row".

    A thousand thanks for this answer. <img src=/S/grin.gif border=0 alt=grin width=15 height=15>