    Hide Non-Working Days on Gantt Chart (MS 98)

    Is there a way to hide and not print the non-working days on the Gantt Chart?

  2. #2
    Silver Lounger GARYPSWANSON's Avatar
    Join Date
    Aug 2001
    Location
    Frederick, Maryland, USA
    Posts
    1,788
    Thanks
    0
    Thanked 2 Times in 2 Posts

    Re: Hide Non-Working Days on Gantt Chart (MS 98)

    Michael,
    I am assuming you are trying to print the gantt view (Correct?) If so, you could try changing the major and minor scale so days are not shown. For example, in the Gantt view, double click on the timescale on the right side of the gantt above the bars. You will see the settings for the Major and Minor scale. Try setting the Major scale to Months and the Minor to weeks or just set the Major to Weeks and the Minor to none. In this view you won't see any days.

    If you need to see days on the gantt, then I don't believe there is any way to restrict non-working days from the view so they won't print.

    HTH
    Regards,

    Gary