    Variable duration of a task (2002)

    I have a task that is designed to span the life of the project. However, I do not want to specify the duration of the task, rather I want the duration to be derived based on other tasks and milestones in the project. As I recall, I have done this with Project Scheduler, but having switched to MSP, I do know how to do this.
    Any thoughts are appreciated.

  2. #2
    Silver Lounger GARYPSWANSON's Avatar
    Join Date
    Aug 2001
    Location
    Frederick, Maryland, USA
    Posts
    1,788
    Thanks
    0
    Thanked 2 Times in 2 Posts

    Re: Variable duration of a task (2002)

    What you are trying to do is create a Hammock task. That is the task is linked as a start to start to one task and a finish to finish to another task.

    In 2000, you can review how to do this by looking at the following link
    http://support.microsoft.com/default.aspx?...kb;EN-US;141733

    This may work in 2002 as well.

    HTH
    Regards,

    Gary
    (It's been a while!)