    Resource Avialability (2002/Professional/Server)

    I hope that someone can help me out. When I am viewing a resources availability in Project Server, I see that the availability for all of resources has a value until the end of august then I see zeros. I have looked at the global calendars and resource calendars and everything looks good for what the resources are available (which is not zero). Is there a setting or something that I am missing that will let me show all of the resources available time in server views.

    Any help would be appreciated. Thank you.

  2. #2
    New Lounger
    Join Date
    Jul 2003
    Posts
    7
    Thanks
    0
    Thanked 0 Times in 0 Posts

    Re: Resource Avialability (2002/Professional/Server)

    Hi there everyone,

    I found an answer to my issue. In the PWA Admin area do the following:

    Logon to Project Web Access as an administrator
    Select Admin > Manage Enterprise Features > OLAP and Resource Availability
    (paraphrasing from memory)
    Set the availability options as you like and publish availability. This is
    set to 4 weeks by default.


    There ya have it. Thanks for your time.

  3. #3
    Silver Lounger GARYPSWANSON's Avatar
    Join Date
    Aug 2001
    Location
    Frederick, Maryland, USA
    Posts
    1,788
    Thanks
    0
    Thanked 2 Times in 2 Posts

    Re: Resource Avialability (2002/Professional/Server)

    Jason,

    Thanks for posting your response so others can benefit. <img src=/S/cheers.gif border=0 alt=cheers width=30 height=16>
    Regards,

    Gary