    Showing schedule against Baseline1 (Project 2000)

    Hi,
    I am looking at the Tracking Gantt and interested in seeing my schedule compared against Baseline1. Note that Project lets you save several baselines, and calls these Baseline, Baseline1, Baseline2, Baseline3, etc. The Tracking Gantt though only shows me the schedule against the original Baseline. I know I did this before, but I can't find the right place to set the option. How do I tell Project to show me my schedule against Baseline1 or Baseline2, etc.
    Thanks
    PaulaG

  2. #2
    Silver Lounger GARYPSWANSON's Avatar
    Join Date
    Aug 2001
    Location
    Frederick, Maryland, USA
    Posts
    1,788
    Thanks
    0
    Thanked 2 Times in 2 Posts

    Re: Showing schedule against Baseline1 (Project 2000)

    Paula,

    Just to check, wouldn't you save one baseline and keep interim plans to track against the original baseline? When you use the save baseline command, you are capturing the interim current start and finish dates into the Start 1 - Start 10 and Finish 1 - Finish 10 fields (select save interim plan option).

    In either event, try Format Bar Style and add the bars you want to show for the particular view you are using. Is this what you are looking for?
    Regards,

    Gary