    Wrong Resource in To Do List (Project 2000 & 2002)

    We are trying to use the "To Do List" Report to give to our project resources as informal timesheets. I select a resource in the drop down box, and the report is formatted for that resource. However, several tasks for a different resource show up in the report. These are not tasks to which both resources are assigned - they are assigned solely to the "other" resource - not the one selected for the report. Does anyone have any ideas as to why this might happen and how it can be fixed? Thanks very much.

  2. #2
    Silver Lounger GARYPSWANSON's Avatar
    Join Date
    Aug 2001
    Frederick, Maryland, USA
    Thanked 2 Times in 2 Posts

    Re: Wrong Resource in To Do List (Project 2000 & 2002)

    The to do list provides data for all tasks associated with the resource selected. I don't know why you are getting other tasks if you say they are not present on the other tasks.

    Try the following:

    Go to Custom Reports and Select the To Do List. Select Edit. Change the table from Entry to Work and re-try running the report.


    (It's been a while!)