    Work Breakdown Structure (98)

    I was wondering if you can update the WBS numbering system after modifying an existing entry (by design or mistake). The WBS updates when you delete or add a task, but I dont know how to do something like an 'F9' update field. I believe it is possible in MS Project 2002. Help wasnt much help unfortunately!

  2. #2
    Silver Lounger GARYPSWANSON's Avatar
    Join Date
    Aug 2001
    Location
    Frederick, Maryland, USA
    Posts
    1,788
    Thanks
    0
    Thanked 2 Times in 2 Posts

    Re: Work Breakdown Structure (98)

    In lieu of F9, go to the Project menu, WBS, define code, and re-number the WBS's. This may cause some unexpected results so good luck.
    Regards,

    Gary
    (It's been a while!)