I have an activity that is scheduled to take five weeks. Department A will be supplying several employees for a total of 10 man weeks and Department B will be supplying several employees for a total of 25 man weeks. When I enter Dept A with 10w, it changes that to 200% since 10 weeks is 200% of 5 weeks. Is there a way to set this up without having to list the specific employees in Dept A and B? I want to do some resource leveling over the entire project.

Ronny