Hi All - this is an extension to my previous post. The attached spread sheet explains what I need to achieve. I'm sure that some Guru has solution. Any ideas
Hi All - this is an extension to my previous post. The attached spread sheet explains what I need to achieve. I'm sure that some Guru has solution. Any ideas

This month, every Windows Secrets subscriber can download a one-chapter excerpt of Windows 7: The Missing Manual.Windows 7: The Missing Manual provides valuable information to help you overcome these difficulties in learning a new operating system. Subscribe today to download your free excerpt.
Is this what you want:
<pre>=IF(G7<>"","Complete",IF(E7="","",IF(E7>TODAY (),"",IF(NETWORKDAYS(E7,TODAY())>0,NETWORKDAYS(E7, TODAY())&" days overdue",""))))
</pre>
Legare Coleman
Legare - thats looks to be just what I need - Thanks - If you ever come to Perth Aust I'll buy you a beer!!