    updating durations (1998)

    Is there a way to update progress of tasks in quantities rather than % eg: if a task is for 25,000 units and progress is (day 1) 6000 (day 2) 15000 (day 3)4000.
    <img src=/S/aussie.gif border=0 alt=aussie width=21 height=22>

  2. #2
    Silver Lounger GARYPSWANSON's Avatar
    Join Date
    Aug 2001
    Location
    Frederick, Maryland, USA
    Posts
    1,788
    Thanks
    0
    Thanked 2 Times in 2 Posts

    Re: updating durations (1998)

    Instead of using % complete, try updating the Actual Work field. This assumes that your task is setup as a material type task without any labor resources.

    If this doesn't work, please provide more information on how the task is setup, resources assigned and type of resource, task type (fixed, effort driven, etc.), duration.

    HTH
    Regards,

    Gary
    (It's been a while!)

  3. #3
    3 Star Lounger
    Join Date
    Mar 2003
    Location
    Beddau, Mid Glamorgan, Wales
    Posts
    289
    Thanks
    0
    Thanked 0 Times in 0 Posts

    Re: updating durations (1998)

    Hi summer - welcome to the lounge.

    You can use the free number fields (Number1 ... ) to create user-defined fields. For example, you could call one Units and another Units Completed.

    Post back if you need guidance on this or on how to show custom fields in a table.

    Tony.
    Regards,

    Tony
    [s] [/s]
    www.SylviArtist.com

  4. #4
    New Lounger
    Join Date
    Apr 2004
    Location
    Melbourne, Australia
    Posts
    12
    Thanks
    0
    Thanked 0 Times in 0 Posts

    Re: updating durations (1998)

    Thank you very much. Such a simple fix and I've been going nuts haha trying to work it out. I have just managed to get upgraded to Project 2000 so I'll see how I go. <img src=/S/clapping.gif border=0 alt=clapping width=19 height=23>
    "By the way this is the best site" I thought I was wondering all alone in a Project cloud

  5. #5
    Silver Lounger GARYPSWANSON's Avatar
    Join Date
    Aug 2001
    Location
    Frederick, Maryland, USA
    Posts
    1,788
    Thanks
    0
    Thanked 2 Times in 2 Posts

    Re: updating durations (1998)

    I am glad the advice worked and the Lounge is helpful. I find it very beneficial as I have learned alot from others. Post back with any questions you may have.
    Regards,

    Gary
    (It's been a while!)