    Resource Units keep changing. (2003)

    I've a task with multiple resourses. One of them shows 200% in units. I try
    to change to 100% and it changes it back. I can't seem to change anything
    that will allow me to change that. Help? I know it's just a combo of effort driven, type, etc. But can't make it work!

    On that same note, how can I tell project to NEVER use anything but 100%.
    These are all people and can only be <= 100%.

  2. #2
    Silver Lounger GARYPSWANSON's Avatar
    Join Date
    Aug 2001
    Location
    Frederick, Maryland, USA
    Posts
    1,788
    Thanks
    0
    Thanked 2 Times in 2 Posts

    Re: Resource Units keep changing. (2003)

    Bryan,

    Is the 200% showing up in the task pane when assigning resources?

    Go to where your resources are setup and check their availability. Also, could you please provide more information on the task. Is it fixed duration, effort driven, etc.

    Any chance you are using multiple resource pools with the same resource name assigned to the task from multiple pools?
    Regards,

    Gary
    (It's been a while!)

  3. #3
    2 Star Lounger
    Join Date
    Jan 2003
    Location
    Greeley, Colorado
    Posts
    188
    Thanks
    8
    Thanked 1 Time in 1 Post

    Re: Resource Units keep changing. -- Resource Pool

    Well I can't tell you what I did [img]/forums/images/smilies/sad.gif[/img], but I got it working this morning. As much as I THINK I understand how this stuff works, I stil sometimes can't figure out why Project is doing something. v2003 is better for me, but ... The dialog looks a bit weird now as the effort driven checkbox is checked AND greyed out but since I changed it to fixed work it makes some sense.

    You mention resource pools. Do you have a good link explaining how they work. When I've set them up for this master/sub project they don't work as I expect. I've tried to make each one the master pool and neither option gave me the results I'm looking for. What I want is for the master project to have it's set of resources, which are available in the sub projects and are leveled across the master and sub-projects. I want additional resources in the sub projects which are only used by them. Right now the resources duplicate. I want the sub projects worked on by the sub project managers and show only their resources and then for it all to roll up into my master project correctly.