    Hello

    I am trying to filter my projects to show all tasks that the baseline finish date (month) is later than date1field(expected date-month). Can anyone help me please.

  2. #2
    Silver Lounger GARYPSWANSON's Avatar
    Join Date
    Aug 2001
    Location
    Frederick, Maryland, USA
    Posts
    1,788
    Thanks
    0
    Thanked 2 Times in 2 Posts

    Re: filters (2000)

    In Project,

    Select Project, Filter, More Filters, New.

    In Field 1, Select Baseline Finish
    In Text, Select Is Greater Then
    In Field 2 Select Date1

    Save and run the filter.

    Does this do what you want?
    Regards,

    Gary