    I am looking for a way, formula, macro ....etc to store a date for when the task is added to the plan. I am trying to avoid adding another field that has to be populated by human interaction. We are using this to track new issues and need a date to put the issues in the proper quarter of the year. We need to count new issues every quarter. This has been a manual process and we are trying to automate it.

  2. #2
    4 Star Lounger
    Join Date
    Sep 2004
    Location
    Sacramento, California, USA
    Posts
    432
    Thanks
    0
    Thanked 0 Times in 0 Posts

    Re: date task created (project 2002)

    There is a field named created and it tracks the date the task was created already in Project. If you right click any field heading in any task based table and select insert column it will give you the field list. Select the created field.
    Carla

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •