    Is there any way to have a constraint be tied to a specific day of the week?
    For example, I have a task that needs to be performed on a weekend in order to be the least disruptive.
    Or would a better option be to create a custom calendar for the resource assigned to the task that would only show weekend availability?

    Thanks,

    Vernon

  2. #2
    4 Star Lounger
    Join Date
    Sep 2004
    Location
    Sacramento, California, USA
    Posts
    432
    Thanks
    0
    Thanked 0 Times in 0 Posts

    Re: Day Of The Week Constraint (Project 2000)

    I would go with the calendar for the resource assigned to the task. You can create a task calendar and assign it to the task if that is better for you, I feel that just adds another level of calendaring to keep track of.