    Dates plotted on calendar view (MS Project 2000 or 2002)

    On the MS Project Calendar View (version 2000 or 2002) is it possible for a user to choose to plot tasks against a set of dates OTHER THAN Start/Finish?

    For instance
    from Start1 to Finish1
    OR
    from Start2 to Finish2
    OR
    from Date1 to Date2, provided Date2 > Date1

  2. #2
    4 Star Lounger
    Join Date
    Sep 2004
    Location
    Sacramento, California, USA
    Posts
    432
    Thanks
    0
    Thanked 0 Times in 0 Posts

    Re: Dates plotted on calendar view (MS Project 2000 or 2002)

    Project does not support custom bar definitions in calendar views. You would be able to create custom bars in any of the Gantt Chart views.