    Varying duration on a hammok task (2003)

    Hi,

    I'm using MS Project Professional 2003 and have come across and find myself stumbling over what (to me at least) should be a fairly easy problem to solve, but for the life of me, I can't figure it out. Perhaps some fresh eyes can help?

    How can I make a task

  2. #2
    4 Star Lounger
    Join Date
    Sep 2004
    Location
    Sacramento, California, USA
    Posts
    432
    Thanks
    0
    Thanked 0 Times in 0 Posts

    Re: Varying duration on a hammok task (2003)

    How about linking task 2 with task 3 FS dependency and using -1h Lag?
    Not sure if this will geve you the result you want. If not repost and I will look at it again.

    Carla

  3. #3
    New Lounger
    Join Date
    Feb 2006
    Posts
    9
    Thanks
    0
    Thanked 0 Times in 0 Posts

    Re: Varying duration on a hammok task (2003)

    Thanks Carla


    I still have not figured this out, and it comes up quite a bit. Let me state it this way

    I have a task that must start on a specific day.

    I want to link it to another task and have it end when the that task starts. (I; have a variable duration) Is this possible?


    For example:
    1) Project awarded (Fix date Jan 1) )
    2) Edit user manuals (to be done from Jan 1 until the Product is ready to be shipped)
    3) Product ship (this is a varying date based on other things in the schedule)

    Can I have project expand and contract task 2 as the project ship moves? But alway start on Jan 1?

  4. #4
    Silver Lounger GARYPSWANSON's Avatar
    Join Date
    Aug 2001
    Location
    Frederick, Maryland, USA
    Posts
    1,788
    Thanks
    0
    Thanked 2 Times in 2 Posts

    Re: Varying duration on a hammok task (2003)

    See <post#= 370401>post 370401</post#> regarding hammock tasks to see if that helps. You basically want a hammock that links as a start to start with one task and a finish to finish to another. HTH
    Regards,

    Gary
    (It's been a while!)

  5. #5
    New Lounger
    Join Date
    Feb 2006
    Posts
    9
    Thanks
    0
    Thanked 0 Times in 0 Posts

    Re: Varying duration on a hammok task (2003)

    That's it! Thank you! I've been trying to figure that out for a while.

    Thank you again. I owe you mutlitple beers. [img]/forums/images/smilies/smile.gif[/img]