    Custom Report (MS Project 2003)

    Hello everyone,

    Does anyone know how to create a custom report in MS Project 2003 that will pull all resource names and only the days that they are scheduled on their calendar as non worked time?

    Each resource has their own calendar which has days scheduled as Nonworking time.

    Thanks.

  2. #2
    4 Star Lounger
    Join Date
    Sep 2004
    Location
    Sacramento, California, USA
    Posts
    432
    Thanks
    0
    Thanked 0 Times in 0 Posts

    Re: Custom Report (MS Project 2003)

    This custom report is the only way that I know to get Project to give you a list of non-working time for resoruces:
    From the menu bar select View Reports
    In the reports dialog box select custom
    In the custom reports dialog box select New
    In the Define new report dialog box select resource. (The monthly calendar option will not give the info you are looking for)
    In the Resource report dialog box on the definition tab name your report
    On the details tab in the resource section check calendar; in the bottom of the details tab select border around details.
    This should give you the start of what you need. It will need to have fields cleaned up and margins cleaned up.
    If you save the finished report to the organizer it will be available to all other project plans you create on your PC

    Carla

  3. #3
    New Lounger
    Join Date
    Jan 2006
    Posts
    4
    Thanks
    0
    Thanked 0 Times in 0 Posts

    Re: Custom Report (MS Project 2003)

    Thank you, that worked! <img src=/S/clapping.gif border=0 alt=clapping width=19 height=23>