Results 1 to 2 of 2
  1. #1
    3 Star Lounger
    Join Date
    Nov 2001
    Location
    Brooklyn, New York, USA
    Posts
    200
    Thanks
    2
    Thanked 0 Times in 0 Posts

    Opposite of Predecessor (Project 03)

    Another basic question. We have the Predecessor column in the Gaant Chart. Want to add the opposite time flow: the dependent column, or whatever you call that.

    Also: we're having trouble keeping the date flow of our related tasks consecutive. The problem is when we change a start date on the predecessor task after both tasks were created, it disconnects the finish to start flow of the dependent task and the dates are then displayed manually.

    Can anyone elaborate for float, lag and lead time?

    Thanks for the tutorial,

  2. #2
    4 Star Lounger
    Join Date
    Sep 2004
    Location
    Sacramento, California, USA
    Posts
    432
    Thanks
    0
    Thanked 0 Times in 0 Posts

    Re: Opposite of Predecessor (Project 03)

    HI,

    To display the opposite of a Predecessor right click the column heading of any table and select Insert Column. Select Successors from the field list. The new added column will be to the left of the selected column.

    Lag time creates a gap between the finish of a Predecessor Task and the start of a Successor task in a dependency relationship. To create a positive number in the lag column in if you are using the Predecessors tab of the Resource Information dialog box. Personally I prefer to use a task without any resources assigned as a placeholder in the alternative of a lag.

    A lead (more often called negative lag) creates an overlap between a Predecessor task and a Successor task. If you have Task 1 as a four day task in a finish to start dependency with Task 2 a 5 day task with 2 days negative lag this means 2 days before the end of Task 1, Task 2 will begin creating 2 days of concurrency. a lead is created by using a negative number in the Lag column of the predecessors tab of the Task Information dialog box.

    Not sure I understand the rest of your question. If you post a small piece of your plan and provide me with a little more explanation I will take a look. To add a Project file to the Lounge I think you have to zip it.

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •