    Adding Resources to a task (Project 2000 SR-1)

    I am working on entering actual hours into a project, and sometimes I get someone that worked on a project they weren't assigned to. When that happens, I think the only solution is to add them to the tast, but that messes up the projected work of the other people assigned to the task. Is there a way to make project evenly distribute the hours between everyone, or is there another solution for this situation.

    Thanks,
    Bithmus

  2. #2
    Super Moderator WebGenii's Avatar
    Join Date
    Jan 2001
    Location
    Redcliff, Alberta, Canada
    Posts
    4,066
    Thanks
    2
    Thanked 5 Times in 5 Posts

    Re: Adding Resources to a task (Project 2000 SR-1)

    Try changing to a Fixed Duration task constraint.
    Attached Images Attached Images
    [b]Catharine Richardson (WebGenii)
    WebGenii Home Page
    Moderator: Spreadsheets, Other MS Apps, Presentation Apps, Visual Basic for Apps, Windows Mobile

  3. #3
    New Lounger
    Join Date
    Jun 2001
    Location
    Florida, USA
    Posts
    7
    Thanks
    0
    Thanked 0 Times in 0 Posts

    Re: Adding Resources to a task (Project 2000 SR-1)

    You also can split your view and adust the resources in the lower pane. Woody's Watch newsletter had an article on this some time ago.