We are using Project Professional 2003 (SP1) and Project Server 2003 (SP1). When a project contains cross-project links and anything in the linked tasks has changed, a dialog box appears when you open the project with the cross-project links. My questions are:

- The Accept "All" option doesn't appear to work. Does anyone know of documented problems with it? Are there any tricks to using it?

- If you choose to accept task changes individually within the dialog box, you may be allowed to highlight more than one line for each task, e.g., one line will indicate that the Start date changed and another line will indicate that the Finish date changed. Do you have to accept each line separately, or if you accept one line for the task, will it accept all changes for that task?

Thanks,