    I want to set a task to run for the entire duration of another set of tasks in my project. For example, I have a set of development tasks that roll up to a single "Develop application" and I want another "Manage Development" task that starts when the first "Develop application" subtask starts, and ends when the last "Develop application" subtask ends.

    The only way I can find of doing this is to either use an "SS" condition with the first subtask and manually adjust the length of the management task so that it ends at the same time as the last subtask, or create an "FF" condition with the last subtask and make the same manual adjustment of the duration. Neither of these automatically responds to changes in the duration of any of the "Develop application" subtasks, which is what I want to happen.

    Have I missed something in the application, or is this simply beyond Project's capabilities?

  2. #2
    4 Star Lounger
    Join Date
    Sep 2004
    Location
    Sacramento, California, USA
    Posts
    432
    Thanks
    0
    Thanked 0 Times in 0 Posts

    Re: Setting Start AND End dates (2000)

    If you have Develop Application on Level 1, then Manage Development on Level 2 under Develop Application, then have the subtask list on Level 3 under Develop Application then as the subtasks adjust both Summary tasks in Level 1 and Level 2 will adjust accordingly.

    Carla

  3. #3
    Silver Lounger GARYPSWANSON's Avatar
    Join Date
    Aug 2001
    Location
    Frederick, Maryland, USA
    Posts
    1,788
    Thanks
    0
    Thanked 2 Times in 2 Posts

    Re: Setting Start AND End dates (2000)

    Regards,

    Gary
    (It's been a while!)

  4. #4
    New Lounger
    Join Date
    Sep 2002
    Location
    Melbourne, Victoria, Australia
    Posts
    19
    Thanks
    0
    Thanked 0 Times in 0 Posts

    Re: Setting Start AND End dates (2000)

    Thank you! That's exactly what I wanted to know.